2022 Street Improvement Project

Construction Update

06.17.22 Fourth Avenue SE work will continue to be construction of curb and gutter in the westerly two blocks.  Second Avenue NW will be closed starting on Monday for removals, core-out, subdrain tile, and crushed stone base placement.

5.31.22 The remainder of 4th Avenue SE, to Main Street will be cored out, subdrain tile added, and crushed stone base placed.  Curb and gutter construction will start at the east end of 4th Avenue SE and work to the west.

5.23.22 Work continues on 4th Avenue Southeast. Crushed stone base will continue to be placed in the block between 1st Street SE and 2nd Street SE.  This work is going well.  The final block of the project, between Main Street and First Street SE will have surfacing removed, core-out, subdrain tile, and crushed stone base placed.  The extent of the work in this block will be subject to rainfall we receive this week.  New curb and gutter construction may start later this week.

5.9.22 and 5.16.22  Construction work on 4th Avenue SE will consist of storm sewer placement, grading of the blocks between 2nd Street SE and 4th Street SE and weather allowing, placement of crushed stone base on the block between 3rd Street SE and 4th Street SE.  Also subject to weather may be removals on the block between 1st Street SE and 2nd Street SE.

5.2.22 Work scheduled for the week of May 2 includes core-out of 4th Avenue SE between 2nd Street SE and 3rd Street SE and subdrain tile placement.   Placement of crushed stone base will be dependent upon weather conditions as a few dry days are needed.

4.25.22 Work for the week of April 25 is scheduled to be:  core-out of 4th Avenue SE between 3rd Street SE and 4th Street SE; subdrain tile construction from the 5th Avenue SE and 4th Street SE intersection to 4th Avenue SE and within the cored out portion of 4th Avenue SE; crushed stone base placement on the cored out portion of 4th Avenue SE.  Work will be subject to weather conditions. 

4.18.2022   Work on 4th Avenue SE is scheduled to start towards the end of the week of April 18th.  Work will start at the easterly end of 4th Avenue SE in the block between 3rd Street SE and 4th Street SE.  A subdrain tile will be extended along the westerly side of 4th Street SE from 5th Ave. SE to 4th Ave. SE as one of the initial work items.  Removals and grading will follow for 4th Avenue SE between 3rd Street SE and 4th Street SE.  There will be no vehicle access to this portion of the project area once removals begin.  Work will continue to the west along 4th Avenue SE.  A more detailed schedule and update will be provided following a contractor meeting on April 20th.

We welcome your comments and feedback about our website!
Click here to send us your comments


© 2012- Tripoli, Iowa.   Site designed and hosted by Web Design by Duhrkopf 

Website Disclaimer: This site provides links to other web sites. These may include links to web sites operated by other government agencies, nonprofit organizations and/or private businesses. Neither the City of Tripoli, nor any agency, officer, or employee of the City of Tripoli warrants the accuracy, reliability or timeliness of any information published by this system, nor endorses any content, viewpoints, products, or services linked to/from this system, and shall not be held liable for any losses caused by reliance on the accuracy, reliability or timeliness of such information. Portions of such information may be incorrect or not current. Any person or entity that relies on any information obtained from this system does so at his or her or its own risk.